03 / AN ILLUSTRATIVE STARTING POINT
A preliminary selected-load illustration
Power in kW and stored energy in kWh are different specifications. Both need to be checked.
5 kWSelected running load
2 hIllustrative duration
~12.3 kWhNominal energy before margins
5 kW × 2 h ÷ (0.90 × 0.90)
A hypothetical 5 kW essential-load group for two hours.
The example is not a measurement of a Luwara property or a survey confirmation.
Assumes 90% usable battery energy and 90% conversion efficiency for explanation only. Actual output, usable capacity, ageing, temperature, reserve and surge requirements change the design. This is not a quoted package or a backup guarantee.
Reference: EIA explanation of power and energy capacity ↗